Logo
ALANGHSE SERVICES
BOAT EMBARKATION PERMIT ALANGHSE-F-07
REV. 01
Controlled Form
SECTION 1: REQUISITION PERMIT IDENTIFICATION
Applicant (Mukadam)VISHAL PANDEY Ship NameVISHAL PANDEY
Loc of Embarkation[ BE_LOC_EMB ] Loc of Disembark[ BE_LOC_DISEMB ]
Workers / PassengersVISHAL PANDEY
Date / Issue Time2026-08-10 / 08:00 AM Valid up to / Permit No.08:00 AM / [ BE_PERMIT_NO ] A/B
JHA No. (If any)[ BE_JHA_NO ]
SECTION 2: ASSOCIATED PERMITS
Safe for Entry (Vessel)
Debunkering Permit
Cold work permit
Other: [ BE_AP_OTHER ]
SECTION 3: WORK SITE PREPARATION / PRECAUTION
WORK AREA & ENVIRONMENT EQUIPMENT & INFRASTRUCTURE PEOPLE, PPE & AUTHORIZATION CONTROLS
Yes
Tide-tables available with Mukadam & operator?
Yes
Wind speed, sea state, forecast checked?
Yes
Clean landing area identified on both sides?
Yes
Embarkation zone kept clear of obstacles?
Yes
Inter-tidal area clear & ongoing work stopped?
Yes
Is any oil leakage visible in the boat?
Yes
Max occupancy of the boat not crossed?
Yes
Passengers in designated space for balance?
Yes
Permit displayed near the Embarkation point?
Yes
Primary/secondary comms tested (Walkie/Mobile)?
Yes
Rescue boat equipped with LSA/Crane?
Yes
Proper access ladder provided to board?
Yes
Are all the moving parts of the boat secured?
Yes
Fuel and lube oil check carried out?
Yes
Emergency contacts placed in boat & Embark points?
Yes
Waterproof bags provided for belongings?
Yes
Trained First aider in boat with first aid kit?
Yes
Food and water arranged for all onboard?
Yes
Boat ride plan discussed with GM/HSE/Mukadam?
Yes
Required to notify Marine Police about ride?
Yes
HSE team member & supervisor clearly identified?
Yes
Personnel having 2 ID cards, stand at embark pt?
Yes
Security available on both sides for head counting?
Yes
De-briefing done before boat ride operation?
Yes
Passengers briefed on safety, smoking ban, balance?
Yes
Are all personnel in boat wearing life jacket?
Yes
Timing of return ride informed to all personnel?
SECTION 4: PPE SECTION 5: EMERGENCY ITEMS
Safety Helmet
Safety Shoes
Ear plug
Dust mask
Spare Life jacket
First Aid Box
Pair of Oars
Rescue boat
Safety Goggles
Cotton gloves
Coveralls
Life Jacket
Life buoy
Rope
Fire Extinguisher
Crane
SECTION 7: AUTHORISATION CARD
PERMIT APPLICANT
I am satisfied that all precaution has been taken and all safety arrangements will be maintained for entire duration of work.
Name: VISHAL PANDEY
Designation: Ship / Yard Supervisor
Signature:
APPROVAL BY HSE DEPARTMENT
I am satisfied with safety precautions and hereby give permission to commence work.
Name: VISHAL PANDEY
Designation: Safety Officer / HSE Manager
Signature:
PERMIT CONTROLLER / PM-GM
Approval by Plot Manager (PM) / General Manager (GM).
Name: VISHAL PANDEY
Designation: PM/GM
Signature:
SECTION 7: MANDATORY WORK RULES
1. नियर मिस कभी भी छुपाने की कोसिस न करे, उसे फौरन सेफ्टी ऑफिसर/HSE प्रबंधक को रिपोर्ट करे
2. जहाज से वापिस आने के तुरंत बाद परमिट सेफ्टी ऑफिसर/HSE प्रबंधक को लौटा दे!
3. यदि कोई उचित तर्क के साथ असुरक्षित महसूस करता है तो यात्रा रद्द कर दें

Mukadam acknowledgement: I have read, understood and explained these instructions to all workers.
Signature: _____________________     Date: 2026-08-10
SECTION 8: PERMIT RETURN
✓/XSTATUSPERSONNAMESIGNATURETIME
Permit is closed, ride is completed MukadamVISHAL PANDEY 08:00 AM
Safety OfficerVISHAL PANDEY
SECTION 10: EMERGENCY CONTACT NUMBERS
SL. NO.DESIGNATIONNAMECONTACT NO.
1 HSE MANAGER ROCKY SINGH 7990404108
2 PLOT MANAGER PRAVIN SHIYAL 79846 07070