SECTION 1: REQUISITION PERMIT IDENTIFICATION
Applicant (Mukadam)VISHAL PANDEY Ship NameVISHAL PANDEY
Location / Work Description[ DB_LOCATION ] - [ DB_DESC ]
Workers / Sub. ContractorVISHAL PANDEY / [ DB_SUB_CONTRACTOR ] ([ DB_SUB_CONTACT ])
Date / Issue Time2026-08-10 / 08:00 AM Valid Up to / Permit No.08:00 AM / [ DB_PERMIT_NO ] A/B
SECTION 2: ASSOCIATED PERMITS
Confined space permit
Safe for Entry (Vessel)
Work at height permit
Other: [ DB_AP_OTHER ]
SECTION 3: WORK SITE PREPARATION / PRECAUTION
WORK AREA & ENVIRONMENT EQUIPMENT & INFRASTRUCTURE PEOPLE, PPE & AUTHORIZATION CONTROLS
Yes
Is the vessel securely moored?
Yes
Is oil boom wrap around hose intact?
Yes
Gas Monitoring Required?
Yes
Is ventilation to the area adequate?
Yes
Are lighting & access route adequate?
Yes
Housekeeping maintained & flammables removed?
Yes
No hot work allowed in nearby area?
Yes
Emergency Assembly Point identified?
Yes
Oil loading area barricaded & stoppers provided?
Yes
Oil tray placed below pump with oil boom?
Yes
First Aid Kit and Oil Spill kit available?
Yes
Oil removal pump kept in confined space?
Yes
Fire equipment available with fire team?
Yes
Portable fire extinguisher at pumping station?
Yes
Inspection of all equipment's/pumps done?
Yes
Electric cables properly insulated?
Yes
Inspection of pipelines/joints/leaks done?
Yes
Drip trays provided under joints?
Yes
Tank connection secured and sealed?
Yes
Availability of equipment in good condition?
Yes
Permit received from competent authority?
Yes
Job Hazard Assessment done?
Yes
Method/clarity of communication established?
Yes
Continuous supervision at inlet/outlet points?
Yes
Procedure for emergency shutdown in place?
Yes
Is the oil removal team trained?
Yes
Are the workers in proper PPE?
Yes
Proper signage for warning displayed?
Yes
Pre-job Meeting done?
Yes
Induction training provided to truck drivers?
SECTION 4: PPE SECTION 5: EMERGENCY ITEMS
Safety Helmet
Dust mask
S.C.B.A set
E.E.B.D
Stretcher
Coveralls
Cotton gloves
Fire suit
Fire Blanket
First Aid Box
Harness (truck)
Latex gloves
Fire Extinguisher
Fire Hose
Sand bucket
Filter mask
Safety Goggles
Wet Gel Blanket
Safety Harness
Mech. Blowers
Ear plug
Disposal suit
Ladder
Rope
SECTION 7: AUTHORISATION CARD
PERMIT APPLICANT
I am satisfied that all precaution has been taken and all safety arrangements will be maintained for entire duration of work.
Name: VISHAL PANDEY
Designation: Ship / Yard Supervisor
Signature:
APPROVAL BY HSE DEPARTMENT
I am satisfied with safety precautions and hereby give permission to commence work.
Name: VISHAL PANDEY
Designation: Safety Officer / HSE Manager
Signature:
PERMIT CONTROLLER / PM-GM
Approval by Plot Manager (PM) / General Manager (GM).
Name: VISHAL PANDEY
Designation: PM/GM
Signature:
SECTION 7: MANDATORY WORK RULES
1. अगर कहीं भी DO NOT ENTER लिखा हुआ हो तो कभी भी अन्दर न जाये और नाही किसी को जाने दे जब तक आपके पास परमिट न हो|
2. नियर मिस कभी भी छुपाने की कोसिस न करे उसे फौरन सेफ्टी ऑफिसर को रिपोर्ट करे |
3. पाइपलाइन/मसिनेरी पार्ट्स खोलने से पहले अपने टूल्स और अन्य वास्तु (जिससे आप काम में लेते है)उसे चेक करना जरुरी है |
4. अगर आपको डी बंकरिंग परमिट मिल गया है और कहीं बंद जगहे में काम करना हो तो बंदस्थान की अलग से अनुमतिलेना आनिवार्य है|
5. किसी भी टैंक की सफाई करने से पहले करने से पहले बंदस्थान की अनुमतिपरमिट लेना आनिवार्य है |

Mukadam acknowledgement: I have read, understood and explained these instructions to all workers.
Signature: _____________________     Date: 2026-08-10
SECTION 8: PERMIT RETURN (PLEASE TICK WHERE APPLICABLE)
✓/XSTATUSPERSONNAMESIGNATURETIME
Permit is closed, job is completed MukadamVISHAL PANDEY 08:00 AM
Safety OfficerVISHAL PANDEY
SECTION 10: EMERGENCY CONTACT NUMBERS
SL. NO.DESIGNATIONNAMECONTACT NO.
1 HSE MANAGER ROCKY SINGH 7990404108
2 PLOT MANAGER PRAVIN SHIYAL 79846 07070