Logo
ALANGHSE SERVICES
HOT WORK PERMIT HWP-04
REV. 01
Controlled Form
SECTION 1: REQUISITION / CONTROL INFORMATION
Date2026-08-10 Applicant Name (Mukadam)VISHAL PANDEY
Issue Time08:00 AM Ship NameVISHAL PANDEY
Valid up to[ HW_VALID ] Location / Work Description[ HW_LOC_DESC ]
Permit No. A/B[ HW_PERMIT_NO ] Name of WorkersVISHAL PANDEY
JHA Report No. (if any)[ HW_JHA ] Name of Attendant[ HW_ATTENDANT ]
Permit No. (Ext. Competent Person)[ HW_EXT_PERSON ]
SECTION 2: ASSOCIATED PERMITS + SECTION 3: ACTIVITY
Confined space
Safe for Entry (Vessel)
Work at height
Other: _________________
Gas cutting
Plasma cutting
Welding
Other: _________________
SECTION 4: COMPLIANCE MATRIX
CHECK / CRITERIAYESNON/AREMARKS
WORK AREA & ENVIRONMENT
1. Pre-job Meeting done
[ Q1_RMK ]
2. Gas Monitoring Required
[ Q2_RMK ]
3. Is there confined space areas? If yes, permit no.
[ Q3_RMK ]
4. Is ventilation to the area adequate?
[ Q4_RMK ]
5. Are lighting & access to the work area adequate?
[ Q5_RMK ]
6. Is the gas cutting hose and torch in good working condition?
[ Q6_RMK ]
7. Equipment to check wind direction
[ Q10_RMK ]
8. Emergency escape route is clean
[ Q11_RMK ]
9. Is the adjacent area cleaned and gas free?
[ Q12_RMK ]
10. Is there oily tank nearby?
[ Q13_RMK ]
11. Adjacent space (oily) if oily, cleaning report to be prepared; if yes, report no.
[ Q14_RMK ]
12. "Safe for hot work" sign displayed?
[ Q15_RMK ]
EQUIPMENT & HOT-WORK CONTROLS
13. Is Flash back arrestor available in gas cutter?
[ Q7_RMK ]
14. Cylinders are in upright condition
[ Q8_RMK ]
15. Soap solution ready near to cylinders
[ Q9_RMK ]
16. Equipment to check wind direction
[ Q10_RMK ]
17. Is Block cleaned, clear of oil and other dangerous or flammable material?
[ Q16_RMK ]
18. Cutting line is cleaned
[ Q17_RMK ]
19. Crane is available to hold the block/section during its final cut - if yes, crane no.
[ Q18_RMK ]
20. Removal of hazardous materials (as per IHM and PCHM) before commencing hot work
[ Q19_RMK ]
21. Is hot work permit received from competent person?
[ Q20_RMK ]
PEOPLE, PPE & AUTHORIZATION
22. Trained worker/Welder
[ Q21_RMK ]
23. Are the gas cutters properly clothed and equipped?
[ Q22_RMK ]
24. Dry surface, in case welding machine or plasma cutter is used
[ Q23_RMK ]
25. Proper earthing before using plasma cutter or welding machine
[ Q24_RMK ]
SECTION 5: PPE + SECTION 6: EMERGENCY READINESS
S.C.B.A set
E.E.B.D
First Aid Box
Cotton gloves
Safety Helmet
Coveralls
Safety Shoes
Ear plug
Fire Hose Standby
Fire Extinguisher
Fire pump ready
Cut resistant gloves
Fire retardant suit
Safety Goggles
Filter mask
Welding shield
Stretcher
Fire Blanket
Fire suit
SECTION 7: JOINT INSPECTION & AUTHORISATION MATRIX
A. PERMIT APPLICANT B. HSE APPROVAL C. PERMIT CONTROLLER / PM-GM
I am satisfied that all precaution has been taken and all safety arrangements will be maintained for entire duration of work.
Name: VISHAL PANDEY
Designation: Ship / Yard Supervisor
Signature:
I am satisfied with safety precautions and hereby give permission to commence work.
Name: VISHAL PANDEY
Designation: Safety Officer / HSE Manager
Signature:
Approval by Plot Manager (PM) / General Manager (GM).
Name: VISHAL PANDEY
Designation: PM/GM
Signature:
SECTION 8: SPECIAL INSTRUCTIONS / ACKNOWLEDGEMENT
1. If "DO NOT ENTER" is displayed anywhere, never enter and do not allow anyone to enter without the required permit.
2. Never try to suppress/report a near miss yourself; immediately report it to the Safety Officer / HSE Manager.
3. Before cutting, check your torch nozzle and other items/equipment being used for the work.
4. Before starting cutting, check for leakage; start work only when no leakage is found.
5. If hot work is permitted and work is required in a confined space or at height, the Safe for Entry / Work at Height permit is mandatory.
6. Remove all flammable materials from the work area before starting hot work.
7. Return the permit to the Safety Officer / HSE Manager immediately after the work is completed.
8. Hot work is prohibited on any pipeline; action will be taken if this is violated.
9. Do not work at any location other than the location for which the permit has been issued.

I have read and understood all instructions above and have explained them to all workers engaged in the work. I will ensure compliance until the work is completed.

Mukadam Signature: _____________________     Date: 2026-08-10
SECTION 9: PERMIT RETURN (PLEASE TICK WHERE APPLICABLE)
✓/XSTATUSPERSON NAMESIGNATURETIME
Permit is closed, job is contd. Please issue new permit MukadamVISHAL PANDEY 08:00 AM
Safety OfficerVISHAL PANDEY
Permit is closed, job is completed MukadamVISHAL PANDEY
Safety OfficerVISHAL PANDEY
Permit is cancelled, as present conditions are not conductive for carrying out the work
NOTE: Permit should not be closed until general housekeeping has been carried out, gas outlets are closed, residual gas has been removed from gas pipelines/hoses, and sections/blocks are in safe condition.
SECTION 10: EMERGENCY CONTACT NUMBERS
SL. NO.DESIGNATIONNAMECONTACT NO.
1 HSE MANAGER ROCKY SINGH 7990404108
2 PLOT MANAGER PRAVIN SHIYAL 79846 07070
Note: SCBA - Self Contained Breathing Apparatus; EEBD - Emergency Escape Breathing Device; Ext. - External; No. - Number; JHA - Job Hazard Assessment.
This Permit is Valid for maximum 08 Hours including rest hours.

FORMAT PREPARED BY: HSE MANAGER APPROVED BY: GENERAL MANAGER