BOAT EMBARKATION PERMIT ALANGHSE-F-07
REV. 01
Controlled Form
STEP 1: REQUISITION PERMIT IDENTIFICATION
Applicant (Mukadam)VISHAL PANDEY Ship NameVISHAL PANDEY
Loc of Embarkation[ BE_LOC_EMB ] Loc of Disembark[ BE_LOC_DISEMB ]
Workers / PassengersVISHAL PANDEY
Date / Issue Time2026-08-10 / 08:00 AM Valid up to / Permit No.08:00 AM / [ BE_PERMIT_NO ] A/B
JHA No. (If any)[ BE_JHA_NO ]
STEP 2: ASSOCIATED PERMITS
Safe for Entry (Vessel)
Debunkering Permit
Cold work permit
Other: [ BE_AP_OTHER ]
STEP 3: PRE-WORK SAFETY VERIFICATION
CRITERIA Y N N/A CRITERIA Y N N/A
1. Boat ride plan discussed with GM/HSE/Mukadam?
15. Is proper access ladder provided to board the boat?
2. Required to notify Marine Police about ride?
16. Are all the moving parts of the boat secured?
3. HSE member and supervisor clearly identified?
17. Is the fuel and lube oil check has been carried out?
4. Tide-tables available with Mukadam & boat operator?
18. Is any oil leakage visible in the boat?
5. Primary & secondary comms agreed (Mobile/Walkie)?
19. Are all personnel in the boat ride wearing the life jacket?
6. Wind speed, sea state and weather forecast checked?
20. Emergency contact numbers placed in boat/Embarkation Points?
7. Clean landing area identified on both sides?
21. Ensured max occupancy of boat has not been crossed?
8. Is embarkation zone kept clear of any obstacles?
22. Passengers in designated space so balance is maintained?
9. Area clear and ongoing work stopped in inter-tidal area?
23. Waterproof bags provided for carrying belongings?
10. Personnel having 2 ID cards, stand at embark pt?
24. Trained First aider available in boat with first aid kit?
11. Security available on both sides for head counting?
25. Food and water arranged for all onboard?
12. Rescue boat equipped with LSA/Crane?
26. Timing of return boat ride informed to all personnel?
13. De-briefing done before the boat ride operation?
27. Is the permit displayed near the Embarkation point?
14. Passengers briefed on safety rules, smoking ban, balance?
STEP 4: PPE / EMERGENCY READINESS
Safety Helmet
Safety Shoes
Ear plug
Dust mask
Safety Goggles
Cotton gloves
Coveralls
Life Jacket
Spare Life jacket
First Aid Box
Pair of Oars
Rescue boat
Life buoy
Rope
Fire Extinguisher
Crane
STEP 5: JOINT INSPECTION / AUTHORISATION
PERMIT APPLICANT
I am satisfied that all precaution has been taken and all safety arrangements will be maintained for entire duration of work.
Name: VISHAL PANDEY
Designation: Ship / Yard Supervisor
Signature:
APPROVAL BY HSE DEPARTMENT
I am satisfied with safety precautions and hereby give permission to commence work.
Name: VISHAL PANDEY
Designation: Safety Officer / HSE Manager
Signature:
PERMIT CONTROLLER / PM-GM
Approval by Plot Manager (PM) / General Manager (GM).
Name: VISHAL PANDEY
Designation: PM/GM
Signature:
STEP 6: SPECIAL INSTRUCTIONS / MUKADAM ACKNOWLEDGEMENT
1. नियर मिस कभी भी छुपाने की कोसिस न करे, उसे फौरन सेफ्टी ऑफिसर/HSE प्रबंधक को रिपोर्ट करे
2. जहाज से वापिस आने के तुरंत बाद परमिट सेफ्टी ऑफिसर/HSE प्रबंधक को लौटा दे!
3. यदि कोई उचित तर्क के साथ असुरक्षित महसूस करता है तो यात्रा रद्द कर दें

Mukadam acknowledgement: I have read, understood and explained these instructions to all workers.
Signature: _____________________     Date: 2026-08-10
STEP 7: PERMIT RETURN
✓/XSTATUSPERSONNAMESIGNATURETIME
Permit is closed, ride is completed MukadamVISHAL PANDEY 08:00 AM
Safety OfficerVISHAL PANDEY
SECTION 10: EMERGENCY CONTACT NUMBERS
SL. NO.DESIGNATIONNAMECONTACT NO.
1 HSE MANAGER ROCKY SINGH 7990404108
2 PLOT MANAGER PRAVIN SHIYAL 79846 07070